The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____. Select one: a. dependency b. feeding buffers c. critical chain scheduling d. crashing

Respuesta :

Answer:

D) crashing

Explanation:

In project management, crashing refers to a technique used to save time on a schedule. When you crash a project, you will add resources to the existing project's activities at the lowest possible cost. You have to analyze how can you save the most amount of time while spending the lowest possible amount of money.