When multiple Scrum teams are working on the same project, they should make sure that each team has different Sprint start dates, in order to ensure better co-ordination and adaptability.
a. true
b. false

Respuesta :

Otras preguntas

what is the meaning behind another brick in the wall
what is the width? 2w + 2(w+6) = 84
why did president Kennedy get assassinated? Tell me your best opinion.
The edge length of a cube with volume 24 cubic units
I need help finishing a question. I used the explanation function on the program, but it didn't specify what to do to get the final answer. I have attached a pi
16. Construct 3 equations starting with x = 5.
Given that R is between S and T, find the measure of TS RS=6 TR=4.5 TS=?
Please explain the steps or this equation 3+p=8
I am thinking of a number. One half is a third of my number. What is my number? Solving in Poly’s 4 Steps.
One of the five reasons young drivers, age 16 to 20 are involved in more collisions than older drivers is lack of driving _________